RETIREMENT FROM THE PRE-DEFINED QUALIFYING POSITION DOES NOT INFUSE AN IMPLIED POWER TO CULMINATE THE ARBITRATION PROCEEDINGS
CASE DIARY |
|
Name of the case |
M/s
Laxmi Continental Construction Co. v. State of U.P. & Anr. |
Application Ref. |
Civil Appeal No. 6797 OF 2008 |
Appellant |
M/s
Laxmi Continental Construction Co. |
Respondent |
State
of U.P. & Anr. |
Judiciary |
Supreme
Court of India |
Bench |
·
Hon’ble Justice M R Shah ·
Hon’ble Justice A S Bopanna |
Date of judgment |
Sept.
20, 2021 |
PART - A: OVERVIEW
· The Apex Court on
the 20th day of September 2021 rendered its judgment in an appeal
preferred by the Appellant in the jurisdiction of the Hon’ble Supreme Court
against the order passed by a bench of Hon’ble Uttaranchal High Court which set
aside the order passed by Civil Judge (Senior Division), Roorkee, which upheld
the award passed by Arbitrator under the Arbitration Act, 1940 (hereinafter “the Arbitration Act”).
· The highest judiciary expounded view on whether condition of retirement of office of a person appointed as an arbitrator, which was set as pre-requisite qualification for appointment as an arbitrator would negate the arbitration proceedings consequent to such retirement.
PART – B: FACTS OF THE
CASE
· The Appellant was
engaged in business of construction, earthwork and undertook related
contract work from various different parties.
· The Appellant and Respondent entered into an agreement through which the Appellant was engaged by the Respondent for earthwork including lining of specific area. The agreement provided that all the disputes and differences between the parties were to be settled through arbitration, which was embedded in clause 52 of the agreement.
· Clause 52 also provided for the mechanism for appointment of arbitrator, wherein it was specifically emphasised that “Within thirty days of receipt of notice from the contractor of his intention to refer the dispute to arbitration, the Chief Engineer shall send to the contractor a list of three officers of the rank of Superintending Engineer or higher, who have not been connected with the work under this contract.” The contractor was to recommend one name to the Chief Engineer, who in turn was to be appointed as the sole arbitrator by the Chief Engineer.
· During the course of the contract work,
several disputes and differences arose between the parties and the matters were
referred to arbitration.
· In pursuance of the clause 52, one Shri
S.S. Manocha, who was also a Chief Engineer was appointed as the sole arbitrator
for adjudging the disputes between the parties. The arbitration proceedings
were held subsequently and both the parties presented their cases including the
necessary documents in support thereof.
·
However, due to the conduct of
Respondent, the proceedings were adjourned at different instances.
· During the proceedings, Shri S.S.
Manocha, the sole arbitrator superannuated as the Chief Engineer on completion
of superannuation age on 30.11.1995. The Respondents contended that the
arbitration proceedings shall not subsist any further since the arbitrator retired
due to superannuation.
· The Appellant instituted an arbitration
suit before Civil Judge (Senior Division), Roorkee under Section 28 of the
Arbitration Act, 1940 praying for extension of time for making the award and
for hearing and conducting the arbitration, which the Judge ruled in favor of
the Appellant and granted a period of 30 days for disposing the proceedings and
passing an award.
· In compliance with the order issued by
Civil Judge, proceedings were held and the arbitrator passed an award directing
the Respondent to pay a sum of Rs.10,97,024.00/- with interest on the said sum
to the Appellant, which the Respondent challenged before the Civil Judge under
Section 30/33 of the Arbitration Act, 1940 contending that the award was void
since the arbitrator retired prior to the conclusion of the proceedings, which
was overruled by the Civil Judge.
· Being dissatisfied by the order passed
by Civil Judge, the Respondent filed an appeal before the Uttaranchal High
Court wherein the High Court opined that conducting arbitration proceedings
consequent to the retirement from the position that facilitated the appointment
as arbitrator would tantamount to misconduct on the part of the arbitrator and
hence the award was liable to be set aside.
· Being aggrieved by the conclusion found by High Court, the Appellant preferred an appeal before the jurisdiction of the Hon’ble Supreme Court.
PART
- C: CONTENTION OF THE PARTIES
C.1. CONTENTIONS OF THE
APPELLANT
The Appellant during the course of appeal to the
Apex Court made the following submissions:
· The High Court
has erred in brushing aside the order passed by Civil Judge and the award
passed by the arbitrator.
· Both parties are
bound by the arbitration carved out under clause 52 of the agreement. Further,
the process of appointment of arbitrator was duly followed and Shri
S.S. Manocha bearing the rank of Chief Engineer was appointed as arbitrator.
· The agreement did not provide that Shri S.S. Manocha would continue as arbitrator till he retires and the
proceedings shall cease to continue once he attains superannuation. In the
absence of an expressed provision, the arbitration proceedings shall continue
even after the retirement of Shri S.S. Manocha from the position of Chief Engineer.
· The Respondent participated in the
arbitration proceedings even after Shri S.S. Manoch attained superannuation,
which was upheld by the Civil Judge, which was failed to be appreciated by the
High Court.
· The order of Civil Judge, Roorkee extending the period of arbitration proceedings consequent to superannuation of the arbitrator remained unchallenged and attained finality.
C.2.
CONTENTIONS OF THE RESPONDENT
The Respondent during the course of appeal to the
Apex Court relied on the following submissions:
· Shri S.S.
Manocha attained the age of superannuation and was not in position to continue
as Chief Engineer thereby bringing an end to his mandate as an arbitrator and a
new arbitrator is required to be nominated pursuant to clause 52 of the
agreement.
· Objection was raised against the
continuance of proceedings consequent to the superannuation of Shri S.S.
Manocha which was ignored and proceedings were held. This was taken on record
by the High Court. Therefore the conduct of S.S. Manocha tantamount to misconduct
and the award passed is liable to be set aside.
· Reliance is placed in Section 4 of the Arbitration Act, emphasis on state amendment to the State of Uttar Pradesh, wherein it is stated that where any appointed arbitrator who neglects or refuses to act, or becomes incapable of acting or dies, the vacancy shall be supplied by the person designated as mentioned in sub-section (1) of Section 4 of the Arbitration Act.
PART
– D: QUESTION OF LAW INVOLVED
The perusal of the case by different levels of
judiciary in the case under consideration has raised the following questions of
law involved:
a. Does the retirement of an officer who was
appointment as an arbitrator pursuant to an agreement endorse the conclusion of
arbitration proceedings thereat?
b. Whether prolongation of arbitration proceedings consequent to retirement of arbitrator tantamount to misconduct?
PART
– E: RULING BY THE APEX COURT
· Upon inspection
of clause 52 of the agreement, it is observed that sole qualification for
appointment as an arbitrator is that he should be the officer of the rank of
the Superintending Engineer or higher.
· Consequent to appointment of a person as an arbitrator, the proceedings shall be convened
under such an arbitrator unless he
incurs the disqualification under the provisions of the Indian Arbitration Act,
1940.
· Clause 52 does
not reflect that superannuation of an arbitrator shall be a ground for
termination of arbitration proceedings.
· Identical
question was answered in case of Himalayan
Construction Co. v. Executive Engineer, Irrigation Division, J&K and Anr.,
(2001) 9 SCC 359, wherein it was reasoned by the apex court that
appointment of an arbitrator considering his designation was a pre-requisite requirement
and any conduct be it by himself or due to the afflux of time consequent to his
appointment does not render the proceedings invalid, unless the arbitrator meets
disqualification under the law.
· Considering Clause
52 of the agreement, it cannot be said that Shri Manocha’s mandate to continue with the arbitration proceedings
would come to an end on his retirement.
· The Civil Judge,
Roorkee after hearing the parties allowed extension to the arbitration
proceedings for a further period of 30 days which was enforced and attained
finality, being unchallenged by the Respondent until the enforcement of such
order. It is not prudent that the issue is to be looked towards again.
· State amendment
through Section 4 does not find substance since arbitrator has not acted
beyond his capacity and it is not right to term that the arbitrator was
incapable of continuing the proceedings considering the reasoning provided
above.
· The Civil Judge,
Roorkee after hearing the parties allowed extension to the arbitration
proceedings for a further period of 30 days. The arbitrator has proceeded to
continue the proceedings consequent to the order by Civil Judge which in so far
does not equate to misconduct on his part.
· The order passed by the High Court deserves to be set aside. The award passed by the arbitrator and the Civil Judge stands restored.
PART – F: ANALYSIS
· Section 2(a) of
the Arbitration Act defines arbitration agreement as to mean a written
agreement to submit present future differences to arbitration, whether an
arbitrator is named therein or not. Section 3 of the Act read with Schedule I sets
out the provisions that shall be implied and deemed to be present in the
arbitration agreement or clause, in the absence of a contrary intention
expressed therein.
· However, upon a
wider inspection it is understood that, save as otherwise for the implied
provisions embedded in Schedule I thereto, all other intentions / provisions
adjoining arbitration are to be necessarily expressed in the arbitration
agreement / clause.
· Hence, unless
the clause specified that the arbitration proceedings shall culminate consequent
to the retirement of the arbitrator, the challenge against the same shall be
devoid of merit as the parties never intended the same at the time when the
clause was drafted.
· Both parties
consciously participated in the arbitration proceedings after the order of
Civil Judge, which in absence of being challenged waived off the jurisdictional
objection against the conduct of the arbitrator.
· The established
proposition with respect to conduct of the arbitrator and the arbitral proceedings
are laid down and flows down from the arbitration agreement. Therefore it can
be rightly termed that aspect of arbitration cannot supersede its Constitution.
The Calcutta High Court in Union of
India v. Surendranath Kanungo and Anr. (2005
(2) ARBLR 106 Cal) postulated that while deciding the question of
jurisdiction in the context of the question raised by the parties it is
necessary to examine the scope and content of arbitration agreement itself in
as much as, the scope and authority of the Arbitrator emanates from the
agreement itself as it is settled position of law.
· The opinion chalked out by Delhi High Court in Lloyd
Insulations (India) Pvt. Ltd. v. Cement Corporation of India Ltd. (1994 (31)
DRJ 86) on the character of an arbitrator is extremely importance and
unmissed. The Court opined that an
arbitrator is deemed to be an independent person and his retirement has no
relevance for his continuation as an arbitrator. Relying on this opinion,
it can be substantiated that designation or position of an arbitrator which,
was relevant at the time of considering his appointment in statutory terms does
not percolate towards the termination of proceedings consequent to his retirement.
· It is imperative
to note the dictum in Union of India and
Others v. M/B. Prabhat Kumar & Brothers (AIR 1994 SC 649). The Apex
Court upheld that the Arbitrator appointed by the Government ceased to be an
arbitrator consequent to his retirement. The terms and conditions with respect to
appointment of an arbitrator, supplementing the arbitration clause, in
particular the language employed in condition 70 categorically stated that a
new arbitrator shall be appointed in place of the former consequent to
retirement. This view was also affirmed consequently in People Co-Operative Labour & Ors. v. Union of India and Anr. (71
(1997) DLT 106).
The Judgment can be accessed at:
https://main.sci.gov.in/supremecourt/2007/20200/20200_2007_43_1501_30172_Judgement_20-Sep-2021.pdf
DISCLAIMER:
This is a personal blog. Any views or opinions
represented in this blog are personal and belong solely to the blog owner and
do not represent those of people, institutions or organizations that the owner
may or may not be associated with in professional or personal capacity, unless
explicitly stated. All content provided on this blog is for informational
purposes only. The owner will not be liable for any losses, injuries or damages
from the display or use of this information.
Comments
Post a Comment